Ultima – Project Update July 2025




It’s been a significant few months at Ultima, with both sales and construction progressing strongly. As Essentia continues to lead the sales campaign, momentum remains high and the project is tracking ahead of expectations.

On-Site Milestones

Civil works have advanced rapidly, marking an important phase for the estate:

  • Bulk earthworks and full cut-and-fill across the site are now complete.
  • Retaining walls have been constructed.
  • Sewer and stormwater works are finished, ensuring the site is fully serviced to support housing delivery.
  • Underground services are well advanced, with sewer infrastructure at 90% completion, water detention and pump station installation more than halfway through, and electrical works now underway.

Market Response to Date

The first two stage releases sold out earlier this year, well ahead of schedule. This response validates both the product and price positioning.

Buyers have shown a clear appetite for:

  • Low-maintenance, high-quality townhomes.
  • A connected lifestyle that balances convenience with contemporary design.

Next Release: Stage 3

With civil works progressing, final preparations for Stage 3 are now underway. Demand indicators remain strong, and we anticipate another highly competitive sales outcome.

Early engagement strategies are already in place, with priority registrations open to ensure qualified buyers are channelled effectively.